Having found the ShorePower, truck electrical stations midway between Huntsville AL and Nashville TN, I decided to do an all electric, round trip to measure times, distances, and costs.
Huntsville To Nashville And Back
Bob Wilson
Having found the ShorePower, truck electrical stations midway between Huntsville AL and Nashville TN, I decided to do an all electric, round trip to measure times, distances, and costs.
Huntsville To Nashville And Back
- Arrive Tennessean Truck Stop - 6:37 to 7:39, started with 70 miles EV indicated at 100% SOC. Tripmeter reports 1:02 hr, 55 mi, average speed 54.0 mph. Connected to ShorePower getting 212VAC @30A, 6.36 kW but though power was on, took about two minutes to contact activation service for 2 hour charge, $3. Had breakfast and used excellent WiFi to plan Nashville destination, Green Hill YMCA, in Nashville. Found a data plate: Model TSE-4, Part: SP-0585-R02, 120/240 VAC, 102 Am NEMA 3Rm Wire Size: 4awg to 3/0, Intertek.
- Arrive Green Hills YMCA EVgo - 9:43 to 10:48, left with 81%, 62 mi indicated. Arrived 13.5% with 11 mi indicated. Total distance 115 mi, 2:08 hr, 55.1 mph, 4.3 mi/kWh. Connected to EVgo which reported: 45 min and 8 seconds, 17.07 kWh, cost $15.75 at 11:36. I returned to charging station at 12:10 AM not realizing the charging session had ended. The e-mail notification was OK but an iPhone SMS text would have been more useful. Had a Lox cream cheese, toasted bagel for lunch.
- Arrive Tennessean Truck Stop - 11:58 to 13:04, left with 96.5%, 69 mi indicated. 1:05 h duration, 60 mi, 3.9 mi/kWh, 56.8 mph. Arrived 12.5%, 9 mi indicated. Connected to ShorePower which was still hot without calling the enable service. Had a bowl of soup and set destination for the HSV fast DC charger. Left with 71% and 59 mi indicated to map distance of 49 mi.
- Arrive HSV Fast DC charger - 14:55 to 15:57, ICE started 30 yards from charger, 6% and 6 mi indicated. Started charger and paid $0.25 parking meter fee.
- Arrived home 17:14.
- The phantom charge is misleading. The last 91-100% charge does not have the same kWh of energy per percent as the lower percentages. This makes sense as the current falls off above 88% so it makes sense we are not storing the same kWh as before. So even though I left with an indicated 10 mile pad, I arrived at the HSV Fast DC charger at the threshold that just started the ICE. I stopped it in about ~10 seconds as I parked.
- It appears ShorePower activation is 'honor system' at the Tennessean Truck Stop. I had to turn on the NEMA 14-50 circuit breaker but it was never turned off by their activation service.
- Every hour of driving is ~2 hours of L2 charging at 208-210 VAC at 30 A. In contrast, a fast DC charger takes about 45 minutes. However, both suffer from a higher indicated charge in the 91-100% SOC level that does not have the same kWh energy level as the 81-90%. What this means is a detour to a fast DC charger needs to be less than an hour or you might as well use a full-power, L2 charger.
- EV costs were $3, $15.75, and $0.25, for a total of $19.00. Had I driven on gas, it would have cost ~$12 and saved nearly 5 hours of charging. The total trip time was ~11 hours for both driving and charging.
Bob Wilson